Kohesio: discover EU projects in your region

project info
Start date: 4 January 2018
End date: 31 December 2022
funding
Fund: Cohesion Fund (CF)
Total budget: 3 452 587,80 €
EU contribution: 3 361 166,20 € (97,35%)
programme
Programming period: 2014-2020
Managing authority: Estrutura com a natureza jurídica de estrutura de missão, criada pelo Decreto-Lei n.º 137/ 2014 de 12 de setembro
European Commission Topic

Environmental Recovery of Quinta do Bispo Mining Area – Phase 1

Carrying out demolition work of the decanting ponds and existing monitoring building and construction of the reservoir and cell for temporary waste disposal, pipelines, drainage, various interventions in the pond of clean water and in the cutting (sealing, paths, drainage, pumping), cleaning and regularisation of water line and contaminated soils, reactivation of the old ETAM and installation of monitoring equipment.

Flag of Portugal  Viseu Dão Lafões Subregion, Portugal