Start date: 1 October 2020
End date: 31 December 2023
funding
Fund: European Regional Development Fund (ERDF)
Total budget: 2 370 514,26 €
EU contribution: 2 370 514,26 € (100%)
programme
Programming period: 2014-2021
Managing authority: Ministerul Dezvoltarii Regionale, Administratiei Publice si Fondurilor Europene

Increasing the distribution capacity of LEA 110 kV D.C. Constanta Nord — Medgidia Nord, Nazarcea — Medgidia 1; Lea 110 kV Medgidia Nord — Mircea Voda Nord; Lea 110 kV Mircea Voda Nord — Mircea Voda — Works to strengthen the electricity grid upstream of the connection point of production capacities in order to take over electricity produced from renewable resources

The overall objective of the project is to increase the level of security in the supply of electricity to consumers and to ensure the technical conditions for the take-over of energy produced from the RES by reducing the limitations imposed on producers from renewable sources under N-1 conditions in operation and increasing the efficiency of the network management. The expected results of the project are summarised in: — 4 upgraded stations (3 upgraded 110/6kV transformer stations: Mircea Voda, Medgidia Nord, Nazarcea and 1 modernised 110 kV connection station Mircea Voda Nord)-14 km reconducted on segments from 4 LEA 110 kV

Flag of Romania  Multiple locations, Romania