The material scope of the project includes the following activities: 1. Superstructure and reconstruction of the SUW building with an underground section of the rainwater sewage system, 2. Demolition of the existing tank (discharger) of rinse water, 3. Construction of two new drainage reservoirs, including an underground section of the drainage system, 4. Modernization of existing retention reservoirs, 5. Making a band around the object. 6. Construction of a photovoltaic installation on the ground. In addition, the project envisages the inclusion of: 6. Orders to develop project documentation 7. Investor supervision orders 8. The main problems of project beneficiaries are: - Threats to the security of water supply with the parameters of water suitable for human consumption for all residents of the Municipality, - Significant degree of consumption of technology functioning in the SUW, - Failure of water transmission systems, including uncontrolled leakages resulting in increased operating costs - High economic indicators of water infrastructure, which, due to the above problems, generate high costs of servicing the SUW. The main objective of the project is to improve water management in the Wadowice Górne Commune. The main objective will be pursued through specific objectives, which will be related to the long-term benefits that will be achieved through the implementation of the project: • increasing the availability of high-quality drinking water in the area covered by the investment, which will contribute to raising the standard of living of the inhabitants of the municipality. • protection of groundwater • improvement of fire protection of the area covered by the investment • increasing the economic, tourist and settlement attractiveness of the Commune's areas • improvement of the quality of services related to water management • reduction of the number of accidents • improvement of the working conditions and safety of SUW employees • reduction of unit costs of water management services • improvement of the image of the commune / town • increase of ecological awareness of residents. The project to improve the functioning of water infrastructure in the area covered by the project is an element of filling the gaps in the water management of the Wadowice Górne Commune and is also an element of strategic thinking about the development of the entire Commune. The existing SUW building supplies water to the inhabitants of the Wadowice commune and parts of the village in the Radomyśl Wielki commune, covering the demand for water for consumption, for agricultural and domestic purposes. Growing demand, technical condition of individual SUW elements and problems with maintaining the required quality of treated water force the need to modernize the existing treatment system. The material scope therefore includes the reconstruction of the existing technological system, increasing its production capacity and improving the quality of treated water and reducing the failure rate of the system. Water management is one of the main factors determining the state of the natural environment and the quality of life of residents. This project also aims to expand and organize water supply management and eliminate existing failures. The layout of the planned construction works allows for the adoption of an optimal schedule for the execution of individual and adopted technological solutions, modern equipment, ensure proper quality and relatively low investment costs. For this purpose, it is necessary to have a well-functioning system that improves water for consumers. In addition, increasing the level of water infrastructure equipment by the elements indicated in the material scope will reduce the distance of the municipality to the more developed areas of the voivodship. The project submitted for funding is a means to solve the identified problems. The objectives and scope of the investment are closely related to the existing problems in the area of water and sewage management of the municipality. The investment has all the permits and is ready to be implemented on the basis of the funds available in this project.