The project will be implemented in the area of: Kielce, Ostrowiec, Starachowice and Litigation. The scope of the project includes the expansion of existing RES installations (micro-installations) with electricity storage facilities operating for their needs in the amount of 566 pcs. The scope of the project includes the supply and installation of energy storages with the capacity of: – 6 kW – 51 units – 7 kW – 46 units – 8 kW – 31 units – 9 kW – 181 units – 10 kW – 63 units - 11 kW -3 pcs - 12 kW -22 pcs Total: 566 pcs. The total capacity of all energy storages under the project will be 4.277 MWe, and the total capacity of 6,4155 MWh. BIELINY - 5 kW - 45 pcs. – 6 kW – 8 units – 7 kW – 12 units – 8 kW – 8 units – 9 kW – 33 units – 10 kW – 8 units - 12 kW - 4 pcs. Total: 118 pcs. TOP - 5 kW - 46 units – 6 kW – 12 units – 7 kW – 8 units – 8 kW – 4 units – 9 kW – 45 units – 10 kW – 17 units - 11 kW - 2 pcs. - 12 kW - 6 pcs. Total: 140 pcs. TOTAL - 5 kW - 12 units – 6 kW – 10 units – 7 kW – 7 units – 8 kW – 5 units – 9 kW – 28 units – 10 kW – 4 units Total: 66 pcs. BUTTERS - 5 kW - 18 pieces – 6 kW – 7 units - 7 kW - 5 pcs. - 7 kW - 5 pcs. – 8 kW – 6 units – 9 kW – 42 units – 10 kW – 23 units - 12 kW - 7pcs Total: 108 pcs. PAWŁÓW - 5 kW - 20 units – 6 kW – 7 units – 7 kW – 7 units – 8 kW – 5 units - 9 kW - 15pcs – 10 kW – 7 units - 12 kW - 3 pcs. Total: 64 pcs. WAŚNIÓW - 5 kW - 28 pcs. - 6 kW - 7 pcs. - 7 kW - 7 pcs. - 8 kW - 3 pcs. - 9 kW -18 pcs. - 10 kW - 4 pcs. - 11 kW - 1 pc - 12 kW - 2 pcs. Total: 70 pcs. Each RES micro-installation extended under the project with energy storage will be used throughout its implementation, as well as durability only for the household's living needs (not related to conducting business and agricultural activity). The scope also includes: -supervisory inspector -promotion of the project As part of the promotion, the Applicant and the Municipality covered by the project will publish on their websites and on social media a short description of the project, place an information board at the place of implementation of the project, on all documents and materials, display in a visible way the colours of the Republic of Poland, the EU mark and the coat of arms of the Świętokrzyskie Province. The investment will be carried out in accordance with the DNSH principle. The implementation of the investment will have a positive impact on: -mitigation of climate change, -adaptation to climate change, -prevention of air pollution. The investment is not significant for marine waters and water resources for the protection and restoration of biodiversity and ecosystems. The long-term objective of the project is to improve air quality in Bielina, Górno, Łączna, Masłów, Pawłów, Waśniów and Świętokrzyskie voivodeships. This will be achieved by reducing pollution and CO2 emissions. The strategic objective of the project is to reduce carbon dioxide emissions. The project is fully in line with the objective of RSO 2.1. Promoting energy efficiency and reducing greenhouse gas emissions (ERDF). The implementation of the project will contribute to the achievement of the objectives set out in the Świętokrzyskie Development Strategy 2030+, i.e.: -reasonable use of natural environment resources with simultaneous efforts to reduce adverse human impact on the environment, -protection of biodiversity and functional-spatial coherence of the natural system, -effective action to prevent and reduce the effects of climate change. The applicant did not start the project before submitting the application. The scope of the project does not require notification/construction permit or obtaining a decision on environmental conditions. The applicant is fully prepared to carry out the project.