The investment will be carried out in the Pawłów agglomeration with a population equivalent (p.e.) of 9259. The planned sewage system will run through the towns of Jadowniki and Rzepin Kolonia. As a result of the investment, a 12.21 km network will be built, including: gravity – 8.67 km, overburden of 2.55 km and overburden of 0.99 km, to which 870 inhabitants will be connected. The implementation of the project will contribute to the sewerage of the agglomeration in 99.89%. Scope of the project: 1. Construction of sanitary sewerage system in Jadowniki, Rzepin Kolonia Due to the terrain, the nature of land development and development, as well as ground and water conditions, a mixed sanitary sewerage system was designed. It is a gravity-pressure system based on mains and household sewage pumping stations. When designing the investment, technical solutions in the field of designing external sewage networks and household canals were included: • Length of main gravitational channels – 8674,5 m of which: PVC pipes Ø200mm class S – 8674,5 m • length of side sections of gravity channels – 2214,5m, of which: PVC pipes Ø200mm class S – 314,0m PISTON PIPE: The total length of the designed piping network from PE100 PN10 SDR17 pipes is 3540,5m of which: • total length of main piping with a diameter of PEØ90x5.4mm – 3426,0m • total length of piping with a diameter of PE Ø63x3,8mm from domestic sewage pumping stations – 114.5m The total number of sewage wells is – 444 units. As part of the project, it is planned to build a monitoring system (SCADA). The monitoring system will perform the following functions: •event-time function, •function - main synoptic window, •logging/logging out of monitoring station operators, •historical alarm function, •current alarm function, •data recording, •control of monitoring station connection with monitored objects or devices, •possible access control to monitored object, •burglar alarm, •remote alarm shutdown function, •object refresh function, •historical trends, •reports. The project provides for the implementation of intelligent systems for the management of water and sewage networks, allowing for efficient and economical use of water resources. The entire built sanitary sewerage system will be inventoried in a GIS class system, which will be used to manage network assets and will create an electronic archive of documents related to the infrastructure. Metering of the water supply network in the Pawłów agglomeration in order to reduce water losses • implementation of the hydraulic and hydrodynamic model of the water supply network 1 pc. •Implementation of hydraulic and hydrodynamic model of sewage system 1 pc. •creation of a flow monitoring point with installation of 8 pcs. •concentrator Construction of a 30 kWp PV installation. The municipality is ready to implement the project, i.e.: •The municipality has the right to dispose of the property for construction purposes, •Decisions on environmental conditions, ref. RRiOŚ.6220.5.2013.M.S of 3 February 2014. (concerns the construction of the sanitary sewerage network in Jadowniki) •Decision No 144/2014 ref. IN-II.7840.1.186.2014 of 1 October 2014 •Decision No 599/14 ref. BK.I.6740.5.187.2014.GK of 17 November 2014 The project promotion will be carried out as described in Section I. The applicant has not yet started the project.