The project retains its original objectives, length of road section designed: 11,28 km; bridges: 4 pcs; passages: 3 pcs; intersections: 2 pcs; parking lots: 2 pcs, specifying that for a unitary approach to implementation and monitoring, the aim was to identify quantifiable and auditable phasing indicators, corresponding to the 2 phases, as follows: o Phase 1 – works executed and paid for until 31 December 2023, i.e. works settled under the design and execution contract, and Phase 2 – works executed and paid for during the eligibility period of PT 2021-2027. In phase 1 were built 3 bridges and 2 passages remaining for phase 2 to build 1 bridge, 1 passage, 2 intersections, 2 parking lots and 11.28 km of road.