The project retains its original objectives, road rehabilitation: 71,512 km; new bridge: 1 pcs; rehabilitated bridges: 8 pcs, specifying that for a unitary approach to implementation and monitoring, the aim was to identify quantifiable and auditable phasing indicators, corresponding to the 2 phases, as follows: Phase 1 – works executed and paid up to the date of this proposal for an addendum to the financing contract, i.e. works settled under the design and execution contract – Phase 2 – works executed and paid during the eligibility period for PT 2021-2027. Thus, in phase 1 were executed 87% of the road works related to the project, 0 new bridges and 0 rehabilitated bridges. In phase 2, the remaining 13% of road works, 1 new bridge and 8 rehabilitated bridges are to be executed.