Start date: 28 December 2018
End date: 30 September 2020
funding
Fund: Cohesion Fund (CF)
Total budget: 810 283,50 €
EU contribution: 588 758,96 € (72,66%)
programme
Programming period: 2014-2020
Managing authority: Ministerstwo obsługujące ministra właściwego ds. rozwoju regionalnego
European Commission Topic

Conversion of 110/15 kV Kleczew station to enable the development of renewable energy

The scope of the project includes the reconstruction of the power station GPZ 110/15 kV Kleczew in order to enable the development of renewable energy. The station is part of a distribution network at a voltage of 110 kV, where electricity is transformed to a voltage of 15 kV.

Flag of Poland  Poznański, Poland