Start date: 28 December 2015
End date: 31 December 2023
funding
Fund: Cohesion Fund (CF)
Total budget: 52 016 450,00 €
EU contribution: 44 213 980,00 € (85%)
programme
Programming period: 2014-2021
Managing authority: Ministerstwo obsługujące ministra właściwego ds. rozwoju regionalnego

Construction of the KST tram line stage III. It is also known for the construction of a two-storey intersection within the street. Opole

The project involves the implementation of the following works: • construction of a new tram line and reconstruction of the existing tram line together with accompanying infrastructure (traction network, traction substations, power grids, etc.), tram stops and bus bays; • reconstruction of the tram loop Krowodrza Górka and construction of the bus and tram loop Górka Narodowa together with the bus and tram terminal on the western side of the planned junction al. 29 November with a designed street. Iwaszki and multi-storey car park in the P&R system; • construction of parking spaces in the P&R system in the area of the Krowodrza Górka tram loop and the intersection of the Wolbromska Trail with ul. Pachoński and in the area of the loop on the National Górka; • construction of two parking lots in the P&R system in the area of Krowodrza Górka tram loop and at the intersection of roads in the footsteps of the Wolbromska Route with ul. Pachoński; • construction of engineering facilities: tunnel in the street. Opole, viaduct over St. Above the Sudola River, a bridge over the Sudoł stream, a footbridge over the Wolbromska Route, a bridge over the Białucha River, a bridge serving as a culvert on the Bibiczanka stream, a railway overpass; • construction and reconstruction of the site’s armament network: telecommunications networks, general sanitary, rainwater, water, gas and heating networks, technological transfusion channels, road lighting, electricity networks nN, SN, WN; • construction, extension and reconstruction of the road system in the area of investment; • execution of other necessary construction works; • extension and integration of Intelligent Transport System (monitoring systems, traffic signalling systems, passenger information, area traffic control).

Flag of Poland  Kraków, Poland