Kohesio: discover EU projects in your region

project info
Start date: 1 January 2014
End date: 31 December 2023
funding
Fund: European Regional Development Fund (ERDF)
Total budget: 30 221 194,00 €
EU contribution: 17 785 442,00 € (58,85%)
programme
Programming period: 2014-2021
Managing authority: Ministerstwo obsługujące ministra właściwego ds. rozwoju regionalnego

Construction of Ostrołęka – Stanisławów line with the construction of Wyszków station and extension of the station in this line

The subject of the project is the construction of a two-track high voltage power line of 400 kV with a length of 110 km (220 km of electricity network) on the Ostrołęka-Stanisławów section. In this section, one station 400 (220)/110 kV Wyszków will be built and two stations will be expanded: 400/220/110 kV Ostrołęka and 400 kV Stanisławów. The aim of the project is to improve the safety and safety of the National Power System in the north-eastern part of Poland, to improve the power supply of the Warsaw agglomeration and the 110 kV network The indirect objective of the project is: a) creating the conditions for increasing the possibility of electricity exchanges with the Lithuanian electricity system while ensuring the safe operation of this connection (b) creating the conditions for power decommissioning from conventional and renewable energy sources

Flag of Poland  Multiple locations, Poland