The aim of the project is to improve the power supply of the city of Poznań through the construction of the power station 110/15/6 kV – GPZ Garbary with connections of WN and SN. The project covers the following tasks: 1. Construction of a power station WN/SN Garbary including: overhead switchgear 110 kV two-section, single system, interior switchgear 15 kV two-section, single system, interior switchgear 6 kV, internal switchboard building 15 kV and 6 kV and ancillary spaces. The planned location of the facility is plots 5/27 and 5/26 in the central part of the city of Poznań. 2. Reconstruction of fragments of the existing 110 kV line – in connection with the construction of a new station GPZ Garbary – including carrying out the necessary dismantling works. 3. Connection of existing cable outlets of 15 kV and 6 kV to the new station GPZ Garbary. All the areas where the project was located are less developed areas. The project will be implemented in turnkey mode.