The subject of the project is the thermal modernisation of one building – Primary School No. 4 in Świdnica (dolnośląskie voivodeship, Świdnicki district, Świdnica, ul. Marcinkowskiego 4-6). So far, energy audits, technical documentation and SW have been developed. Construction work has not been started. The applicant submitted the construction works – Starosta Świdnicki issued Decision No WB.6743.1078.2015 of 2015-12-30 on the absence of opposition to the notified works. The project is a stand-alone unit of analysis and covers all the investment tasks necessary to ensure the functionality and interoperability of the infrastructure as soon as the material scope is completed. The implementation of additional investment tasks not included in the material scope is not required for the launch of the project products. The project includes Task No. 1 Thermomodernisation of SP No. 4 in Świdnica and Task No. 2 Promotional measures. Task 1: IT’S 1.1. Preparatory work, i.e. Technical documentation; IT’S 1.2. Construction works – SP building no. 4 in Świdnica (including modernisation of building partitions; replacement of opening carpentry, modernisation of hot water installations; modernisation of the heating system; modernisation of lighting for energy-saving LEDs; IT’S 1.3. It’s investor supervision. Task 2: IT’S 2.1. Purchase of 1 information board; IT’S 2.2. Purchase of 1 commemorative plaque; IT’S 2.3. Cost-free forms of promotion. The Municipality of Świdnica will be the applicant, Investor, Beneficiary and Operator of the investment. The following departments will be responsible for the project: Department of Urban Investments; The Financial Division; Department of Public Procurement and Tenders. The applicant shall have appropriate organisational and technical facilities; administrative capacity and operational capacity to implement and maintain the project over a period of sustainability. The project will be managed by the PCM method, in a participatory form targeting tasks and objectives.