The subject of the project is the construction of a system of bicycle paths in the city of Grudziądz.The beneficiary of the project is the municipality-city Grudziądz. It is worth noting, however, that due to the nature of the investment, users of bicycle paths should be included among the final beneficiaries. The project will be implemented in the city of Grudziądz. The main problem identified is the high emissions of toxic exhaust components.The main objective of the project is to reduce emissions of toxic exhaust components.The material scope of the investment and the work schedule includes the following activities: 1. Project documentation: 10. 2015-12.2016 2 Feasibility study, WOD update: 11.2017.3. Land purchases: 05.2017-03.2018 4. Land breakdowns: 01.2017-04.2018.5. Construction work: a) I stage: 08.2017-05.2018 (b) Stage II and stage III: 10.2017-07.2018.6. Investor supervision: a) I stage: 08.2017-06.2018 (b) Stage II and stage III: 11.2017-08.2018.7. Promotion: 03.2018-08.2018