Start date: 16 June 2016
End date: 31 December 2021
funding
Fund: Cohesion Fund (CF)
Total budget: 2 725 167,87 €
EU contribution: 2 148 453,36 € (78,84%)
programme
Programming period: 2014-2021
Managing authority: Ministerstwo obsługujące ministra właściwego ds. rozwoju regionalnego

Reconstruction of the overhead line 110 kV Sieradz – Jawor – Błaszki to connect renewable energy sources in the area of the Sieradz County in the Łódź region.

The subject of the project is the reconstruction of the line 110 kV from the 110/15 kV Sieradz station to the 110/15 kV Błaszki station with a length of 38.159 km (calculated per track). The conversion of the above line is intended to enable the connection of: • 25.3 MW – Wind Farm Wójcice, • 14.7 MW – Wind Farm Wróblew – the farm is connected, but the state of the network limited its full use. The limitation is 14,7 MW. The implementation of the project will remove barriers causing limitation, • 0.7 MW – 2 pieces on the side of SB in the Błaszki station • 43.05 MW Farma Wiatrowa Warta • 2.7 MW – 4 pieces on the SN side of the station Jawor and Błaszki The project will be implemented in the Łódź Voivodeship, in the Sieradzkie District, in municipalities: Sieradz, Sparrow and Blankets. The project covers the reconstruction of: • single-track sections of line 110 kV "Sieradz – Jawor" (from station 110/15 kV "Sieradz" to pole No 103) and "Jawor – Błaszki" (from station 110/15 kV Błaszki" to pole 103) with a total length of 21.357 km and • two-track line 110 kV on the section from column no. 103 to the station "Jawor" with tracks "Sieradz – Jawor" and "Jawor – Błaszki”.

Flag of Poland  Sieradzki, Poland