Login
English
Select your language
Close
bg
български
es
español
cs
čeština
da
dansk
de
Deutsch
et
eesti
el
ελληνικά
en
English
fr
français
ga
Gaeilge
hr
hrvatski
it
italiano
lv
latviešu
lt
lietuvių
hu
magyar
mt
Malti
nl
Nederlands
pl
polski
pt
português
ro
română
sk
slovenčina
sl
slovenščina
fi
suomi
sv
svenska
Search
Search
Search
Kohesio: discover EU projects in your region
Menu
Close
Close
Menu
Back
Home
Projects
Beneficiaries
Services
FAQ
Home
>
Beneficiaries
>
Beneficiary Details
Graph
More
more info
Start date:
29 April 2016
End date:
31 December 2023
Number of projects:
21
Total budget:
71 974 614,14 €
EU contribution:
46 479 059,72 €
Website:
n/a
Country:
Explore more:
n/a
funds
CF:
32 835 672,07 €
ERDF:
13 643 387,65 €
PGE DYSTRYBUCJA S.A.
share on
Facebook
Twitter
Linkedin
Email
report an issue
PROJECTS
1 - 15 of 21
PROJECT
TOTAL BUDGET
EU CONTRIBUTION
FUND
Construction of line 110 kV Nowy Żmigród-Iwonicz to enable the development of renewable energy in the southern part of Podkarpackie voivodship
7 102 604,28 €
5 234 947,47 €
CF
Insulated network 6 kV m. Rzeszowa at a voltage of 15 kV – modernisation of three 110/SN stations: Rzeszów Staromieście, Staroniva and Rzeszów Centralna.
6 002 248,07 €
3 968 570,03 €
ERDF
Construction of GPZ Felin
5 201 820,00 €
3 795 415,08 €
CF
Construction of the 110 kV line between Annopol and Budzyń
6 616 854,25 €
3 755 182,41 €
CF
Reconstruction of GPZ Budzyń
6 157 710,00 €
3 472 285,07 €
CF
Modernisation of 110/15 kV RPZ Ruda station – extension of 110 kV switchgear to H5 system to ensure the possibility of RES connection
3 346 726,50 €
2 457 668,28 €
CF
Construction of the WN Brzezińska-Radogoszcz line
4 340 407,50 €
2 343 820,05 €
CF
Construction of GPZ Huszlew
3 883 581,00 €
2 342 873,17 €
CF
Construction of GPZ Grójec 2
3 526 200,00 €
2 181 964,20 €
ERDF
Reconstruction of the overhead line 110 kV Sieradz – Jawor – Błaszki to connect renewable energy sources in the area of the Sieradz County in the Łódź region.
2 725 167,87 €
2 148 453,36 €
CF
Expansion of GPZ Wilkołaz
2 776 527,00 €
2 023 278,78 €
CF
Streamlining of distribution infrastructure through investments in the main power stations: Modernisation of the 110/15 kV Wieluń station to ensure the possibility of RES connection
2 815 485,53 €
2 012 591,87 €
CF
Modernisation of medium-voltage lines in the Olecko and Świętojno communes in order to create conditions for connection of power generation units from renewable sources
1 930 383,15 €
1 640 825,68 €
ERDF
Reconstruction of the 110 kV line between Poniatowa and Nałęczów in order to enable the development of renewable energy.
2 627 586,00 €
1 630 569,70 €
CF
Construction of the 110 kV line to Korczowa station and station 110/15 kV Korczowa to connect customers and renewable energy sources from the border area of Korczów border crossing point.
4 442 720,41 €
1 618 586,83 €
CF
Visualise as a network
Open in the EU Knowledge Graph